The majority of track has been laid to take Edinburgh’s tram to Newhaven as the scheme enters the final phase of construction works, the council has reported.
More than 3km of track – 70% of the total to be laid – is now in the ground as part of the Trams to Newhaven project, which remains on schedule to begin revenue services in spring 2023, delivered within the £207.3m budget.
The main construction work on three of the eight new tram stops is also complete, while over 3km of drainage (66% of the total) and almost 4km of communications ducting (82% of the total) serving the tram and wider area has been installed.
Additionally, construction is largely finished on several key sections of the route, other than some localised works, including Constitution Street, between Constitution Place and Queen Charlotte Street, and Ocean Terminal to Rennie’s Isle.
Operational tram stops on Princes Street and St Andrew Square will reopen this week following their temporary closure. These were closed to allow for the removal of the York Place tram stop and installation of new infrastructure there connecting the existing line to the new one, the City of Edinburgh Council said.
Testing and commissioning will take place this winter, with a review of the specific completion dates for remaining sections carried out. This has resulted in some changes affecting certain sections due to various unavoidable factors such as complex utilities diversions, archaeological finds and an industry wide shortage of materials, though the council added this is not expected to affect the final completion date.
Cllr Lesley Macinnes, transport and environment convener, said: “It’s clear that the Trams to Newhaven project is well on its way to completion, as these figures show, and before long we’ll be testing trams on the streets of Leith. Next week, we’ll also see the return of the existing service to the city centre, which I’m sure will be great news for many.
“Of course, while this project will bring significant benefits to the area, we know that its construction has impacted all those who live and work nearby, and I’d like to thank them for their patience during the last two years.
“As we enter the final year of work to deliver the tram line, we’ve had to make some changes to the programme due to issues out with our control. I want to assure communities along the route that we’re doing everything we can to mitigate the impacts of this, and that we’re still on track to begin providing the service by spring next year.”